Barbrook Lane, Tiptree - Highway improvements

Works location and photos

View of Grove Road/Barbrook Lane junction
View of site entrance on Barbrook Lane

About the scheme

As part of the planning consent granted for the new Bloor Homes development on Barbrook Lane in Tiptree, highway improvements are to be carried out. 

Arrangements have now been made for these works to take place from 31 January 2022 to construct a new junction on Barbrook Lane, install a raised table at the junction between Barbrook Lane and Grove Road, and resurface Barbrook Lane.

The works will be phased with the support of road closures, which reduce the overall construction time compared with alternative traffic management.

The works

The works are expected to begin on Monday 31 January 2022 and continue until the end of April 2022, subject to weather being suitable and no unexpected issues arising.  

Construction will be carried out in phases with traffic management, including road closures, adjusted according to the activities being carried out to ensure the safety of the public and the workforce.

The developer will be working collaboratively with third party organisations to enable use of the road closures for their service connections to the new development where possible, thus reducing the likelihood of future inconvenience to residents.

What is involved and how it may affect you

The majority of these works will take place between the hours of 8am and 5pm, Monday to Friday with occasional Saturdays working up to 1pm. 

A small section of Barbrook Lane will be closed throughout the works, with vehicular access provided to properties situated within the closure.   

Pedestrian access through the closure will be maintained.

Provisional  dates

Works and proposed traffic restrictions

Phase 1:

Approximately 6 weeks from 31 January 2022 to 11 March 2022.

Access into the new development, service connection works and foul sewer connection

Traffic management: Temporary closure of Barbrook Lane, refer to drawing 2009-481-278G 

Phase 2:

From 14 March 2022 to 22 April 2022.

Construction of the raised table and double yellow lining. 

Please note that the consultation period of the Traffic Regulation Order has ended. Objections received will require the correct legal procedures to take place before works can start for the raised table as well as the double yellow lining. 

Provisional arrangements - subject to change:

Temporary closure of Grove Road (24 hours a day) refer to drawing no. 2009-481-278G 

Phase 3:

From 25 April 2022 to 27 April 2022

Resurfacing Barbrook Lane

Temporary closure of Barbrook Lane (24 hours a day) refer to drawing no. 2009-481-278G

Traffic management will be reviewed and adjusted where necessary according to the works being undertaken and dates may be subject to change.

Drivers are recommended to take additional care when driving through the area.

Further information

Please note that the programme may be subject to change at short notice so please observe signage on site and check this webpage for updates received from the developer.

The developer will ensure that residents and businesses are kept informed of key information and any changes.

For details about other roadworks in the area please visit: One.Network and the @essexhighways twitter feed.