Utility companies and their works
On this page you will find:
Working with the utility companies
As the Highways Authority for Essex, we work closely with utility companies who supply power, water and telecoms to our communities. Regular meetings are held with each utility company to review their performance and discuss any issues.
Everyone who wants to carry out activities on Essex's roads must apply through the Essex County Council Permit Scheme. This ensures a fair, regulated and co-ordinated approach that minimises disruption.
Under The Traffic Management Act 2004, Essex County Council cannot prioritise our own works over those of the utility companies.
Reinstating roads, footways and verges
After utility companies complete their works, it is vital they reinstate roads, footways and verges properly to keep our residents safe.
The Reinstatement of Openings in the Highway (SROH) is the national statutory code mandated by the Department for Transport (DFT) under Section 71 of the New Roads and Street Works Act 1991 (NRSWA).
The SROH outlines approved materials, expected standards of workmanship and levels of performance. Utility companies must follow this code so their work is safe and long-lasting.
The code applies to both interim and permanent reinstatements, both during the works and throughout the relevant guarantee period. There is no legal requirement for utility companies to go beyond these specifications.
'Temporary tarmac' may be used for up to six months. This solution helps us keep the roads open and allows the utility companies to carry out their necessary works in an efficient way.
Utility companies do not have to reinstate the full width of a road or footway. In fact, reinstating only the area that is dug up is quicker and less disruptive. However, our Streetworks team may sometimes request an enhanced reinstatement, for example across the full width of a recently resurfaced road after emergency works have been completed.
Although there is no legal requirement for the utility companies to comply, agreements are often reached through the working relationships we have built over time.
Reinstatement after major resurfacing works
If we're planning major resurfacing works, we can issue a notice to restrict utility companies digging up roads and reinstating them for a timescale of typically two years. However, emergency works and new customer connections are excluded from this period of restriction.
For more information see our Section 58 restrictions page.
Guarantees
In most cases, the guarantee period for reinstatements is two years. During this time, utility companies are responsible for any repairs or maintenance required due to issues with their reinstatement work.
If the reinstatement is deeper than 1.5 metres or if it has a concrete surface, the guarantee period is extended to three years. Deeper excavations and concrete surfaces are generally considered to be more complex and require a longer guarantee period to ensure the quality and longevity of the reinstatement.
Once the guarantee period expires, the responsibility for any future repairs or maintenance shifts to the Highway Authority. Essex County Council is the Highway Authority for Essex.
Inspections
The New Roads and Streetworks Act 1991 allows Highway Authorities to conduct a specific number of inspections on utility companies' reinstatement works. For each of these inspections, regardless of the outcome, the Highway Authority can charge a fee of £50.
These inspections occur at different stages including during the works, within six months of completion, and within three months before the end of the guarantee period.
Essex County Council officers may also visit sites at any time in response to reports about substandard workmanship. They carry out thousands of these inspections each year to make sure all works meet the highest standards.
If the work is not up to standard
We use the Department for Transport's 'Street Manager' IT system to record any defective reinstatements which sends an alert to the utility company involved. They have 27 days to fix the problem but can request more time to avoid work 'clashes'. A further inspection is then carried out.
If these timings are not met, our senior officers raise it with senior managers at the utility company. If a resolution is not found, we can use our own contractors to complete the works and charge the utility company.
If a utility company consistently fails to meet the required standards, additional rechargeable inspections may be conducted, accompanied by an intensified escalation and discussion process.
Frequent performance assessment meetings will be held until the inspection results demonstrate acceptable levels of conformity. The utility company will be expected to develop an action plan outlining how they will improve their practices.
Fines
There is no specific legislation in place to impose fines on utility companies solely for poor reinstatement quality. Whilst not a 'fine' we raise charges to recover officer time spent inspecting reinstatements that do not meet standards.
Other circumstances where we can fine utility companies
Where a permit to work is granted and there is a breach of the conditions placed upon the permit, the penalty amount is set at £120 (£80 if paid early). If a utility company conducts work without a permit, the fine is £500 (£300 if paid early). If the utility company's works continue beyond the permit end date and no additional time-period is granted, a daily charge can be imposed.
The daily charge varies according to the works' type and the status of the road, and serves as a deterrent to prevent over-running works and ensure compliance with permit regulations. Charges applied here could be up to several thousand pounds. For more information, see our Essex County Council Permit Scheme web page.
Why are there sometimes no operatives on site?
While it may appear that there is no one working on site. There can be many reasons for this. Most commonly, it is due to hand overs between teams with differing specialisms. Operatives will undertake different parts of the same job, for example, excavate the hole, install new apparatus, or repair existing equipment, refill the hole, and then tarmac the area. It will also most likely be a separate specialist contractor who supplies any form of traffic management needed such as temporary traffic signals.
Other reasons why a site might appear 'un-manned' may include the need for highway surface materials to cure before the surface can be reopened to traffic use. This is especially relevant when concrete has been used in any reinstatement.
Where emergency gas leaks are being repaired, it may be necessary for a works site to be left unmanned whilst gas is safely vented into the atmosphere from open excavations prior to determining the exact location of the leak and undertaking necessary repairs.
Damage to grassed areas
If the utility company damages grass areas near their works, even if they haven't directly dug up those areas, we can ask them to repair the damage. But we need to gather evidence to show the damage was caused by the works, such as documents, photos or other supporting material.
By holding utility companies responsible for repairing any damage they cause, including non-excavation-related damage to grass areas, Essex County Council ensures that the landscaping of the area is restored to an acceptable condition.
Emergency works
In the event of an emergency, or a situation where they decide unplanned works must be started immediately such as a burst water main or gas leak, or loss of supplies to premises (including telecommunications), utility companies can notify as late as two hours after work starts.
A permit is still required but can't be refused. It can be a challenge to co-ordinate these unplanned works around other works already underway.
Our officers may allow more time for emergency works where this enables a replacement of a section of utility apparatus instead of just a repair. This will reduce the need for future visits to the same location.
What we are doing to minimise disruption from unplanned works
We place appropriate conditions on the permits granted for emergency or 'immediate' works to minimise disruption. They are inspected in the same way as other works.
Safety considerations
The legal obligations regarding safety measures during streetworks and roadworks on Essex's roads are outlined in the statutory code Safety at Street Works and Roadworks: A Code of Practice, New Roads and Streetworks Act, 1991.
This code specifies the requirements for traffic and pedestrian management, signing and guarding at works carried out on the highway. More on this can be found in the Traffic Signs Manual.
Fibre, broadband and mobile operators
The volume of work by fibre companies looks set to continue for several years, so we have recruited a Streetworks officer to focus exclusively on fibre infrastructure.
We cannot influence where, when and how fibre and mobile operators site their commercial networks. The permits we grant to them relate only to the co-ordination of works and do not indicate any type of planning approval regarding the installation of cables, cabinets, poles or masts.
The Electronic Communications Code sets out rights in Schedule 3A of the Communications Act 2003 that are designed to facilitate the installation and maintenance of electronic communications networks on, under and over ground.
Siting of cabinets, poles and masts
Almost all fibre and mobile network operators have obtained 'Code operator' status, which subjects them to various conditions and restrictions including an obligation to comply with either the 'Code of Practice concerning the siting of cabinets and poles' or the 'Code of Practice for Wireless Development'.
Most cabinets, poles and masts up to 30 metres do not require full planning approval, as they are deployed using Permitted Development rights under the Town and Country Planning (General Permitted Development) (England) Order 2015.
The operators only need to notify the local planning authority about their plans prior to the infrastructure being installed. This means there is little or no opportunity for the local planning authority, residents and businesses to engage in this process. Across Essex, it is the borough, city or district council who are the local planning authority.
Damage to utility company equipment
The responsibility for repairing or replacing frames, covers, chambers, and above-ground boxes lies with the owner of the equipment, whether it is the Highway Authority or a utility company.
When we find out about damage to this equipment, we will identify the owner and report the issue to them. If there is an immediate threat to safety, we will make the location safe before we report it.
If you know who owns the equipment, you can contact the utility companies to report it.
There is no legislation covering the required speed or response time for utility companies to deal with these reports. Essex County Council does not possess any enforcement powers over utility companies if they think their response is too slow or inadequate.
In such cases, the resolution of the reported issues is dependent on the cooperation and responsiveness of the utility companies involved. Essex County Council can raise the matter with them but does not have direct control over the companies' actions or the ability to enforce a specific timeframe for repairs or replacements.