Local Highway Panels Terms of Reference and Members' Guide

Terms of reference

The Local Highway Panel is responsible for recommending the annual LHP programme for submission to the Cabinet Member for Highway Infrastructure and Sustainable Transport.
The Chairs Panel is accountable for consideration of schemes that are out of the scope of the Local Highway Panels (LHPs) as set out in the LHP Terms of Reference.

Local Highway Panels Members' Guide

Introduction and scope

This Members' Guide has been produced to detail those scheme types that are open to District Panels to implement. The list of these 20 scheme types is shown below. Any scheme types that are not detailed below and within this Members Guide can be elevated to the Chairs Panel where sufficient justification of the scheme is proven.

  1. Signage
  2. Dropped Kerbs
  3. Vehicle Activated Signs/Speed Indicator Device
  4. Road Markings
  5. School Keep Clear Road Markings
  6. Bollards
  7. Gateway Features
  8. Parking
  9. Bus Shelters
  10. Salt Bins
  11. Crossing Upgrades
  12. Pedestrian Guardrail
  13. Speed Limit Reductions
  14. Cycle Parking
  15. Raised Kerbs
  16. Quiet Lanes
  17. Wig-Wags
  18. Traffic Calming
  19. Tactile Paving
  20. Handrailing

Sections 1 to 20 below provide a summary of what considerations are required for each category listed above to ensure the intervention chosen is the most suitable and practical for the local environment; indicative costs and timeframes for implementation are also given where possible and can be used as a guide. A more detailed cost estimate will be provided during the validation stage with all risks and/or assumptions clearly identified. Where appropriate, each section will describe alternative options that could be considered to identify the most suitable intervention, whether this is due to the local environment, safety, or ongoing maintenance requirements.

Each section is a guide to what is possible, and during the validation process a full range of measures will be considered and discussed, with the most appropriate measure being recommend for consideration to the supporting Member.

This guide is a reference to new works that the Panel can recommend for funding. The purpose of the Local Highway Panel is to make recommendations on additions or amendments to the highway; it does not include maintenance functions such as refreshing road markings, repairing damaged bollards, etc. Those items that are considered to be highway maintenance should be directed to the appropriate department.

It is recommended that Members understand and give appropriate consideration to our Vision Zero / Safe System approach to reducing the number of accidents year on year across the network through the practice of safe design and only installing measures that are strictly necessary without creating additional clutter and more hazards on the network. Further information on Vision Zero and its ambition is contained below.

Vision Zero – Delivering Safe Roads

Vision Zero logo

Essex County Council has an aspiration for ZERO road deaths and serious injuries (DSIs) on its roads by 2040. To drive action towards this aspiration (Vision Zero), we have set a challenging target to have no more than 355 DSIs by 2030.

However, for the last 2 years our figures have been increasing and there were 839 DSIs in 2023.

We need to eliminate 70 DSIs per year to achieve our target.

As a member of the Safer Essex Roads Partnership (SERP), we work with our partners to deliver road safety education, enforcement, training and publicity campaigns to high risk target groups. This improves awareness of risks, legislation and penalties and offers people tools and techniques to help them comply with road traffic laws.

The Safe System approach accepts that, as humans, road users will continue to make mistakes, but evidence shows that the roads and roadsides could be designed and maintained to prevent almost all road deaths and serious injuries. The Safe System acknowledges that collisions may still occur, but if the kinetic energy can be reduced to that which a human body can withstand, then death or a serious injury does not need to be the result.

As the Highway Authority for Essex, we are almost solely responsible for what changes are made to our roads and, as such, have the power to prioritise safety and make many changes to save 833 lives and 13,430 serious injuries between now and 2040.

We know what highway features present risk to different road users and we know how to reduce and eliminate most of these risks. There will always be constraints, such as the space we have available at the roadside and available budget but, with every scheme, even if it is just one sign that is being requested:

We must ensure that we do not introduce risk to any type of road user.

For further information about Vision Zero and the Safe System approach please visit the SERP website.

All Members are encouraged to sign the Vision Zero Pledge to show support for a road network free from death and serious injury and to encourage all residents to do the same.

No one should die on Essex roads.

Members' Guides

Introduction

Signs will only be provided on the network when a clear need has been identified. Sign clutter on the network is both confusing to road users and can have a detrimental impact on safety, as well as creating an additional maintenance responsibility for the Council.

All requests for signage will need to be fully compliant with the Traffic Signs Regulations and General Directions and any local Policy or Guidance that has been adopted by the Council.

Things to consider

Considerations that will determine a site’s suitability for additional signage include but are not limited to:

  • Is there sufficient physical space within the adopted highway?
  • Will there be sufficient visibility of the sign for drivers?
  • Will the sign hinder pedestrian or other user groups?
  • Are there any statutory undertakers apparatus underneath the highway which might require relocation and therefore make the cost of installation unaffordable?

Tourism signs are not funded through LHP. Those businesses wishing to apply for tourism signs can do so via the Visit Essex website.

Traffic mirrors shall not be considered for installation on the network as they do not meet DfT requirements and are actively discouraged. Where visibility is the issue alternative measures should be considered such as cutting back vegetation or the repositioning of boundary hedges or fences to properties at the landowner’s expense.

Where the request for signing is for the prohibition of a movement or for banning certain vehicles from specific locations then evidence will need to be presented that shows there is a problem that needs addressing and that the proposal does not have a detrimental impact on a business operating. It also needs to be recognised that certain vehicle types, such as HGVs, often have legitimate access requirements that cannot be prohibited, such as for deliveries.

Signage that relates to a new development is agreed in advance and will have been considered appropriate at the time of agreement. A period of time will need to be given throughout the construction of the new development as traffic patterns change and as the development becomes fully occupied. If post development an issue continues to persist then the Panel may wish to address the issue, however it is recommended to allow traffic patterns to stabilise for a period of time following completion of the development before any additional signage is considered.

Signage on a larger scale can be considered where there is evidence that traffic is using routes that are not appropriate, in order to reinforce the intended route through or around a town or village, such as the principal routes identified on the network.

An existing sign may become obscured or damaged over time. Where a sign is obscured by vegetation a check will need to be made to determine ownership, as vegetation that is in private ownership is the responsibility of the landowner and would be covered by enforcement if there is a persistent problem. Where the vegetation is deemed to be within the highway boundary, this would be deemed a maintenance function and a request for trimming back the vegetation can be logged via the reporting tool. Where signs are being damaged by passing traffic, these should also be raised to the maintenance teams via the reporting tool. If there is a risk to safety then this can be raised via Members Enquiries for immediate attention.

Vision Zero Considerations: Many road users each year die because they hit objects after they have left the carriageway. Examples of features which have led to a death include trees, telegraph poles, sign poles, ditches, ponds, wooden fences, embankments etc.

We must therefore ensure that any features are essential and are protected or passively safe to ensure they do not create risk.

We must ensure that we do not introduce features that cannot or will not be maintained and that we do not introduce features that will be obscured by vegetation.

Motorcyclists are the highest risk group, comprising about 2% of traffic but 25% of DSIs and they require more protection. Many are young riders in urban areas who could be protected by lower speeds, better road/place design and less street clutter, others are more susceptible to poor surfaces including debris, inspection covers, unlit obstructions such as central refuges and unprotected signposts.

  • Each person involved in each scheme, from the scheme promoter to the designer to the constructor needs to ask themselves what impact the scheme will have on the risk to all users but especially riders.

Costs and timeframes

Costs and timeframes for the design and installation of signs vary depending on the nature of the sign itself. Where an existing post can be used there is a reduced cost as only the sign plate itself will need to be erected, whereas if it’s a new sign in a location where there isn’t an existing and appropriate post to be used then there will be a need for a new sign post and foundation. Where the speed limit of the adjacent road is in excess of 50mph then there will be a need for a passively safe post and foundation system to be used which will increase costs further. The costs in the table below provide an indicative range, but they are dependent upon the existing environment.

 
Design
Constuction
 
Fee
Duration
Cost
Duration
Standard Sign Face, Post and Foundation (no TRO) £4,250 6 weeks £5,210 6 weeks
Standard Sign Face, Post and Foundation (with TRO) £6,050 18 weeks £5,210 6 weeks
Standard Sign Face with Passively Safe System (no TRO) £4,250 8 weeks £5,210 6 weeks
Standard Sign Face with Passively Safe System (with TRO) £6,050 18 weeks £5,210 6 weeks

The design duration is measured from the point in time where the scheme has been commenced by the allocated Engineer. The construction durations include the minimum mobilisation time required to provide sufficient time to process the works information and mobilise personnel to undertake the works.

Where a TRO receives an objection additional cost, and time will be incurred on the scheme to either remove the objections through consultation with the objector or for a CMA to be processed. These costs and timescales are dependent upon the number of objections received.

Introduction

Pedestrians will at some point on their journey need to informally cross the carriageway to gain access to destinations on the opposite footway.

 

These informal crossing points (dropped kerbs) can be provided where the presence of a formal crossing point, i.e. Zebra, Puffin or Toucan crossing is not currently available or justifiable under the required criteria.

Things to consider

Informal crossing points with dropped kerbs will be installed accompanied by tactile paving to aid visually impaired pedestrians to locate the crossing point. Considerations that will determine a site’s suitability for a dropped kerb crossing point include but are not limited to:

  • Ensuring that there are suitable locations on each footway directly opposite each to provide a perpendicular crossing point
  • Whether there may be a need to provide additional drainage directly upstream of the crossing to ensure no ponding of surface water occurs at the crossing itself
  • The location of statutory undertakers equipment, as the costs associated with diverting this equipment can be significant, so an alternative location may be required to keep the costs of the design and installation proportional

The dropped kerbs in this guide pertain to pedestrians only. Vehicle crossings for private access into properties are not permitted through the LHP and would need to be applied for (and funded by) the resident/property owner directly. Details of the application process can be found on the Essex Highways website

Costs and timeframes

Based on previous schemes, the estimated cost and typical timeframe associated with the design and installation of a simple dropped kerb crossing are provided in the table below, dependent upon the site conditions at the desired location.  Design and installation costs for a dropped crossing scheme will be considerably higher where other considerations come into play, such as drainage amendments that may need to be included. The additional cost that could be incurred will be made clear in advance of any design taking place.

Should additional drainage features to remove any potential surface water ponding be required and where there is no existing system to connect to within the highway the costs associated with providing one would become significant and may undermine the viability of the scheme.

Timescales given below for the installation of a standard dropped crossing include the minimum mobilisation time required to allow sufficient time for the Contractors processes and mobilisation of plant and personnel to undertake the works.

 
Design
Constuction
 
Fee
Duration
Cost
Duration
Standard Dropped Crossing £5,350 3 weeks £5,500 6 weeks
Standard Dropped Crossing with additional drainage £7,250 8 weeks £10,450 8 weeks

The design duration is measured from the point in time where the scheme has been commenced by the allocated Engineer. The construction durations include the minimum mobilisation time required to provide sufficient time to process the works information and mobilise personnel to undertake the works.

Introduction

Vehicular Activated Signs (VAS) and Speed Indicator Devices (SID) are signs with illuminated messages that flash when vehicles are travelling above a set trigger speed.

There are two categories of vehicle activated signs:

  • Permanent VAS are signs that are permanently mounted on a pole installed within the highway
  • Temporary VAS are signs that may be moved around several locations either to be attached to poles or inserted into sockets already installed within the highway, which include speed indicator devices.

Things to consider

VAS signs are not enforceable as they are designed to increase driver awareness of the signed speed limit or to highlight a hazard.

Any VAS that are required in order to highlight a hazard are generally used as part of road safety measures where advanced warning of a hazard needs to be reinforced to reduce the potential for further incidents at that location. These signs will be assessed and installed by the Road Safety Team and are not permissible for LHP. This is to ensure drivers do not become over accustomed to seeing these types of signs, desensitising their effectiveness.

All requests for permanent speed VAS at site specific locations or for temporary speed VAS can be made through the LHP. The criteria to be met for these signs are that the average vehicle speed is 10mph above the posted speed limit. Those locations that do not meet this criterion will not be processed by the LHP.

District or Parish councils are able to procure their own VAS providing the asset is retained under license by them for any ongoing maintenance. This can be done via the Essex Highways VAS webpage - https://www.essexhighways.org/applications/apply-to-install-a-vas-or-sid-illuminated-sign.

Prior to LHP recommending VAS schemes, consideration to the ongoing maintenance cost for LHP installed units will need to be given as this will impact the limited ECC revenue budget.

Similarly to traffic signs, considerations that will determine a site’s suitability for VAS signage include but are not limited to:

  • Is there sufficient physical space within the adopted highway?
  • Will there be sufficient visibility of the sign for drivers?
  • Will the sign hinder pedestrian or other user groups?
  • Are there any statutory undertakers apparatus underneath the highway which might require relocation and therefore make the cost of installation unaffordable?

Costs and timeframes

Typical cost and timeframes associated with the design and installation of VAS units will depend on the mounting method and site constraints. Where a VAS can be accommodated on an existing asset this will reduce the design and installation costs, however, if a new post and foundation are required then the costs will increase. Typical prices for installation for the two types are below.

 
Design
Constuction
 
Fee
Duration
Cost
Duration
Mounted on an Existing Asset £4,250 8 weeks £5,520 10 weeks
Mounted on a new Post and Foundation £4,950 8 weeks £10,025 10 weeks

The design duration is measured from the point in time where the scheme has been commenced by the allocated Engineer. The construction durations include the minimum mobilisation time required to provide sufficient time to process the works information and mobilise personnel to undertake the works.

Introduction

Road Markings on the public highway are governed by the Traffic Signs Manual and Traffic Signs Regulations and General Directions 2016 (TSRGD) which are used by engineers to ensure that road markings are correctly installed and where backed by a Traffic Regulation Order are legally enforceable. It ensures that road markings are consistent across the UK and are easily understood by road users.

Under LHP, road markings will only be provided on the network when a clear need has been identified, to ensure the markings are appropriate for the location and meet the TSRGD.

Things to consider

All requests for road markings will need to consider:

  • Compliance with the TSRGD and any local Policy or Guidance that has been adopted by the Council.
  • Costs of ongoing maintenance of carriageway markings. The lifespan of road markings depends on the amount of traffic, the location of the lines and the condition of the road surface.

Disabled parking bays are not funded via LHP. All applications before disabled parking bays must be submitted via the the council's website to ensure they are assessed correctly.

Where the request for road markings has been made due to degradation, the request for repainting these should be raised to the maintenance teams via the reporting tool.

The Essex Parking Partnerships should be consulted on the installation of parking restrictions.

Costs and timeframes

The design costs and estimated timeframes for road markings are given below, dependent upon the nature of the markings. Standard road markings that don’t require Traffic Regulation Orders (TRO) are more straightforward and can be delivered quickly. Where the requested road marking comes with a TRO then additional time and resource will be required, and should the TRO receive objections then further time and resource will be required. Should there be objections to deal with or a CMA (Cabinet Member Action) is required the cost, and timescales will be confirmed once the full details have been understood.

The cost associated with the installation of road markings will be dependant up the nature of the road as this will dictate the traffic management requirements. It is also worth noting that there is a minimum charge associated with road markings (for a unit to attend the location) so the cost for a single marking can appear to be high. The cost for road markings on a standard route that only requires minimal traffic management is given below and will take a single shift to complete. Where a more complicated traffic management system is required, these costs will be supplied once the full details are understood.

 
Design
Constuction
 
Fee
Duration
Cost
Duration
Road Markings (no TRO) £4,250 8 weeks £2,500 6 weeks
Road Markings (with TRO) £6,050 18 weeks £2,500 6 weeks

The design duration is measured from the point in time where the scheme has been commenced by the allocated Engineer. The construction durations include the minimum mobilisation time required to provide sufficient time to process the works information and mobilise personnel to undertake the works.

Where a TRO receives an objection additional cost, and time will be incurred on the scheme to either remove the objections through consultation with the objector or for a CMA to be processed. These costs and timescales are dependent upon the number of objections received.

Introduction

As for all road markings on the public highway, school Keep Clear markings are governed by the Traffic Signs Manual and Traffic Signs Regulations and General Directions 2016 (TSRGD). 

The restrictions associated with School Keep Clear markings are limited to the relevant school opening and closing times. A TRO is required to ensure that the road markings are legally enforceable.

 It is not intended that Keep Clear markings are used outside all schools, only where it is necessary for pupils to cross the road.

The Essex Parking Partnerships should be consulted on the installation of parking restrictions.

Things to consider

At each location, the following shall be considered:

  • Each location shall be considered on its own merits, but good visibility is required in both directions of pedestrians by drivers (which is the purpose of the markings).
  • The minimum length of the road marking is 25.56m and this can be increased up to 3m per zig-zag, to a maximum of 43.56m. The overall length may be increased by increments of 6m through the addition of a complete set of zig-zag modules on each side.
  • The marking will need to be accompanied by an upright sign and will require a TRO to ensure it is enforceable. These restrictions will be limited to the relevant school opening and closing times for the peak times 08:00-09:30 and 14:30-16:00, although exceptions can be made to this if a strong case is put forward including the use at the school of a preschool playgroup.
  • No vehicles are permitted to stop, including vehicles displaying a Bue Badge, during these times and dates, even for picking up or setting down passengers. This also applies to loading and unloading of vehicles and also school contract vehicle services.
  • School keep clear markings shall not be used to address parking issues around schools, this should be addressed through the use of single or double yellow lines.

Costs and timeframes

The design cost associated with school keep clear markings given below is similar to standard road markings, the only increase required is to accommodate the TRO process.  Where objections or CMAs need to be drafted, the additional cost for this work will be supplied once the requirement is known. The duration of the design is given below, noting that any additional time for objections or CMAs will made clear at a later date.

The cost for the installation of Keep Clear road markings and the associated signs will be dependent upon the traffic management requirements. As these works will be directly outside schools the timeframe for installation will generally be programmed outside of term times.

 
Design
Constuction
 
Fee
Duration
Cost
Duration
School Keep Clear Markings £4,250 8 weeks £6,720 6 weeks

The design duration is measured from the point in time where the scheme has been commenced by the allocated Engineer. The construction durations include the minimum mobilisation time required to provide sufficient time to process the works information and mobilise personnel to undertake the works.

Where a TRO receives an objection additional cost, and time will be incurred on the scheme to either remove the objections through consultation with the objector or for a CMA to be processed. These costs and timescales are dependent upon the number of objections received.

Introduction

Bollards can be used for different purposes, including as a deterrent or restriction. The installation of bollards needs to be given careful consideration and should be limited in their use to situations when no other alternatives are available.

The type and design of bollards must comply with conservation and other local requirements.

Things to consider

Bollards often restrict the width of a footway and restrict certain pedestrian user groups from legally accessing pedestrian routes, as well as creating an additional maintenance burden for ECC, so their use needs to be limited.

Where bollards are being considered as a deterrent to stop powered two wheeled vehicles from using a section of footway or an alleyway, bollards are not the suitable solution. Instead, this type of activity should be reported to the Police as this is illegal and is therefore an enforcement issue rather than a highway issue.

Where bollards are being proposed to stop vehicles parking on footways and verges then double yellow lines shall be considered as this can then be enforced. Where it would be expected for double yellow lines to become contentious locally, then consideration shall be given to using a higher kerb face to stop vehicles mounting the verge, although a higher kerb face for footways is not always achievable given the costs associated with the resurfacing or reconstruction of the footway itself to accommodate them.

Planters or planting can be used as an alternative to bollards where they can be accommodated, however, to ensure they are properly maintained then it is recommended that the local Parish, District, local businesses or local resident groups take ownership of the asset post-installation and maintain them under license.

The installation of bollards should be a final option where no other alternatives can be made to work due to the existing environment and will need to consider any local conservation areas, so the correct type of bollard is installed.

Vision Zero Considerations: Many road users each year die because they hit objects after they have left the carriageway. Examples of features which have led to a death include trees, telegraph poles, sign poles, ditches, ponds, wooden fences, embankments etc.

  • We must therefore ensure that any features are essential and are protected or passively safe to ensure they do not create risk.
  • We must ensure that we do not introduce features that cannot or will not be maintained and that we do not introduce features that will be obscured by vegetation.

Motorcyclists are the highest risk group, comprising about 2% of traffic but 25% of DSIs and they require more protection. Many are young riders in urban areas who could be protected by lower speeds, better road/place design and less street clutter, others are more susceptible to poor surfaces including debris, inspection covers, unlit obstructions such as central refuges and unprotected signposts.

  • Each person involved in each scheme, from the scheme promoter to the designer to the constructor needs to ask themselves what impact the scheme will have on the risk to all users but especially riders.

Costs and timeframes

Typical design and installation costs and timeframes for the installation of bollards are given below. They will be dependent upon the site constraints, such as location, below ground apparatus (i.e., statutory undertakers equipment), and the number and type of bollard being installed.

 
Design
Constuction
 
Fee
Duration
Cost
Duration
Standard Sign Face, Post and Foundation (no TRO) £6,200 6 weeks £9,750 6 weeks

The design duration is measured from the point in time where the scheme has been commenced by the allocated Engineer. The construction durations include the minimum mobilisation time required to provide sufficient time to process the works information and mobilise personnel to undertake the works.

Introduction

These provide a visual clue to the start of a village can be effective in reducing speeds on the approach to a village.

The Parish or District Council will need to take on the future maintenance of these features under licence depending on what features it includes, e.g. planting or planters.

Things to consider

Other traffic calming works may be combined with a gateway, these could include pinch points, buildouts, islands, and rumble devices, together with changes of carriageway colour and/or texture and the use of appropriate signing. Where changes in the surface of the carriageway are used it will be most effective if they start at the gateway location, rather than in advance of it. This helps to give greater prominence to the gateway itself.

Most speed reduction achieved by a gateway treatment can be extremely local and may be eroded over time. To achieve the most beneficial effect, other traffic calming features will have to be located close to the gateway and extend over the length of road over which the speeds need to be contained.

Gateway features cannot be used to prevent access, so therefore both the horizontal and vertical elements of the gateway must be constructed so that it can be negotiated by any vehicle entitled to use the road.

To achieve the maximum speed reduction possible the gateway must be conspicuous and within any aesthetic constraints imposed by the location, and colours should contrast with the surroundings. Should a coloured surfacing be considered, or rumble strips or markings from an on- carriageway perspective, then the area should normally be at least 5m in length, so it is clearly visible from a distance. Longer lengths up to 10m can improve conspicuity but beyond this may detract from the effect of the gateway. Edge line markings, such as ‘Dragon Teeth’ can make the gateway appear narrower than it is whilst still allowing larger vehicles to overrun these areas if necessary.

A gateway needs to be sighted so that drivers do not encounter them suddenly as this can be hazardous and may not bring about the desired reduction in speeds. The gateway will need to be visible over at least the stopping distance for the 85th percentile of the approach speeds. Basing the distance on the current speed limit will often not be sufficient and speed survey measures will be needed to identify the 85th percentile. Site inspections will confirm whether the stopping site distance is sufficient.

Physical measures, such as buildouts, chicanes and pinch-points can also be used as a narrowing effect and enhance the effect of the gateway and to reduce overall carriageway widths. Islands will need to be appropriately signed and sufficient lane widths retained to suit all vehicles likely to use the gateway. Where farm equipment or specialist commercial or military vehicles have to negotiate a gateway, it can be helpful to use ghost island markings or overrun areas.

A gateway feature comprised of vertical features alone is unlikely to influence vehicle speeds. Where a reduction in speeds is being sought it is recommended that gateways are used in conjunction with horizontal elements. When choosing the location of the gateway there is a need to ensure there is sufficient width to accommodate the vertical elements and that sufficient set back from the edge of the carriageway is available to ensure vehicles cannot come into contact with them. The location of these elements in a footway or cycleway path should be avoided unless there is sufficient space remaining to allow the safe and convenient passage of pedestrians and cyclists and provide sufficient headroom.

Vision Zero Considerations: Many road users each year die because they hit objects after they have left the carriageway. Examples of features which have led to a death include trees, telegraph poles, sign poles, ditches, ponds, wooden fences, embankments etc.

  • We must therefore ensure that any features are essential and are protected or passively safe to ensure they do not create risk.
  • We must ensure that we do not introduce features that cannot or will not be maintained and that we do not introduce features that will be obscured by vegetation.

Motorcyclists are the highest risk group, comprising about 2% of traffic but 25% of DSIs and they require more protection. Many are young riders in urban areas who could be protected by lower speeds, better road/place design and less street clutter, others are more susceptible to poor surfaces including debris, inspection covers, unlit obstructions such as central refuges and unprotected signposts.

  • Each person involved in each scheme, from the scheme promoter to the designer to the constructor needs to ask themselves what impact the scheme will have on the risk to all users but especially riders.

Costs and timeframes

The design and installation costs of gateways are dependent on the types of measures that are going to be used so it is not practical to be able to give an indication of cost until all the details are known. This also applies to the design and construction durations as this is also subject to the interventions being considered.

 
Design
Constuction
 
Fee
Duration
Cost
Duration
Gateway Features To be determined scheme by scheme

The design duration is measured from the point in time where the scheme has been commenced by the allocated Engineer. The construction durations include the minimum mobilisation time required to provide sufficient time to process the works information and mobilise personnel to undertake the works.

Where a TRO receives an objection additional cost, and time will be incurred on the scheme to either remove the objections through consultation with the objector or for a CMA to be processed. These costs and timescales are dependent upon the number of objections received.

Introduction

Both on and off-road parking can be a problem which can be considered by the LHP for funding of solutions.

Introduction of parking restrictions can be extremely contentious and displacement needs to be considered. Essex Parking Partnerships should be consulted on proposals or options prior to progressing a scheme.

Things to consider

ECC will only directly implement parking schemes that meet one or more of the following criteria:

  • They have been identified as necessary to tackle congestion.
  • They reduce road traffic casualties in line with ECC criteria.
  • Are funded through developer contributions that have been identified as a requirement for the planning approval of a local development.

The LHP can only become involved in funding parking restrictions which are required as part of an LHP scheme.

Parking on grass verges can create significant problems and any remedial action to prevent parking on the verges needs careful consideration, as any action may result in additional unwanted parking in surrounding areas.

The enforcement of parking restrictions depends on several things. The availability of civil enforcement officers, the type of restriction and the local circumstances. There are only a limited number of traffic enforcement officers, and they cannot be everywhere at once. If there is a particular issue that requires enforcement, then the relevant Parking Partnership should be contacted directly. Limited waiting restrictions require two separate visits. The first identifies the vehicle parked at the time of the visit, with the second visit then made after the posted time period allowed for parking. A common enforcement issue in some locations is that as soon as the officer leaves the area the vehicles will return. Schools, cash points and takeaway locations are the most difficult to enforce.

The two main types of enforceable waiting restrictions are prohibitive waiting and permissive waiting restrictions. Prohibitive restrictions are indicated by yellow road markings and the times of control will be indicated by accompanying signs, unless they are double yellow.

Permissive restrictions are indicated by white parking bays and the times of the control are also indicated by the accompanying signs. The signs will indicate who can use the parking bay and any limits on its use, such as length of stay. Some bays may also be identified on the carriageway by white letters such as ‘disabled’, ‘doctors’, ‘loading’, or ‘permit holders only’.

All parking restrictions require a TRO and must be consulted on. This is a legal requirement, and all road users are entitled to comment on proposals and object or support them. The detail of the proposed restriction detailed in the TRO must be accompanied by a Statement of Reason which must show that it addresses one or more of the following factors.

  • Safety
  • Congestion
  • Environment

Where objections are received, they need to be formally considered. This could involve modifying a proposal or in some cases abandoning it completely. The outcome of any public consultation can never be accurately predicted and can be a lengthy process.

Costs and timeframes

The cost and timescales associated with the design of parking restrictions and the associated TRO are difficult to quantify as it is dependent upon the specific factors on site and the issues trying to be addressed. Once all available information behind the issue and the intended intervention is understood an accurate cost and timescale will be provided, but it would exclude the costs associated with any objections until they are also known.

The construction costs and timeframe can be indicative as it often a single visit for the marking and associated signs, provided it is a straightforward solution, and the traffic management requirements are not too onerous.

 
Design
Constuction
 
Fee
Duration
Cost
Duration
Parking (no TRO) £4,250 8 weeks £2,500 6 weeks
Parking (with TRO) £6,050 18 weeks £2,500 6 weeks

The design duration is measured from the point in time where the scheme has been commenced by the allocated Engineer. The construction durations include the minimum mobilisation time required to provide sufficient time to process the works information and mobilise personnel to undertake the works.

Where a TRO receives an objection additional cost, and time will be incurred on the scheme to either remove the objections through consultation with the objector or for a CMA to be processed. These costs and timescales are dependent upon the number of objections received.

Introduction

This section of the Members Guide will be updated following the Members Briefing sessions that are scheduled for September 2024.

To be confirmed

Things to consider

To be confirmed

Vision Zero Considerations: People wishing to place shelters to protect bus passengers must consider the movements these people will make to get on and off the bus. If shelters are placed on the shared surfaces and have opaque sides then cyclists passing the shelter may collide with people stepping out of the shelter. Where shelters are on footways it is still possible that e-scooters and both cycles and e-bikes may be using this surface illegally. We are aware this happens and are unlikely to be able to prevent it so we need to ensure that we design with this issue in mind.

  • The Safe System requires us to design for what we know humans will do. We need to make the safe course of action the easiest course of action.

Costs and timeframes

To be confirmed

 
Design
Constuction
 
Fee
Duration
Cost
Duration
Bus shelters TBC TBC TBC TBC

To be confirmed

Introduction

The need for new salt bins and their installation can be recommended by the LHP.

There are numerous issues to consider in order to identify an appropriate location for it to remain functional.

Things to consider

The proposed location of a bin will be checked for suitability to ensure it is safe to access for stocking and use and must be positioned where visibility for drivers is not reduced from the minimum standard criteria.

Salt bins will not be provided in the following circumstances:

  • In private areas or commercial premises.
  • Within 200m of another salt bin.
  • Where they would obstruct the passage of pedestrians.
  • Where the location would reduce visibility for traffic or pedestrians.
  • Where traffic management would be required when installing or stocking.
  • Where the location is on a treated part of the network.

Careful consideration is required so that salt bins remain functional as far as possible. These include:

  • Stealing of salt – some bins are emptied soon after stocking or for resale.
  • Private use – the salt is for use on the public highway only, however reports are made of the salt being use for private use i.e. driveways or on private land.
  • Vandalism/Damage – an on-going maintenance concern.
  • Contamination – Some bins are used as rubbish bins. Any contaminated waste requires emptying and disposal prior to filling.
  • Non-use – some bins are not used and require the salt to be chipped out prior to re-stocking as it has solidified over the year.

Should an existing ECC owned bin prove problematic because of any of the above, Essex Highways reserves the right to remove it.

If the proposed bin location meets all of the criteria below, then the LHP can fund the installation and thereafter Essex Highways will stock and maintain it:

  • The location is on a non-treated part of the network i.e. it does not receive precautionary salting. If a salt bin is on a corner of a treated and non-treated road it will be marked as non-treated.
  • The road is on a steep incline with a gradient greater than 5% for a minimum length of 50m or there are sharp bends with less than 500m radius and a speed limit greater than 30mph.
  • Not within 200m of another salt bin.

Costs and timeframes

The timescale for delivery of salt bins is subject to the availability of the salt bins and will be confirmed once stocks are checked or the order of a bin has been made.

 
Design
Constuction
 
Fee
Duration
Cost
Duration
Salt bins (filled) £500  weeks £5,210 6 weeks

The design duration is measured from the point in time where the scheme has been commenced by the allocated Engineer. The construction durations include the minimum mobilisation time required to provide sufficient time to process the works information and mobilise personnel to undertake the works.

Introduction

LHP can be used to fund limited upgrades to existing zebra crossing and the provision of new pedestrian refuge islands to enhance and provide safer locations to cross the carriageway.

Things to consider

Enhancements to Zebra Crossings will be limited to:

  • the replacement of old beacons with new Halo beacons
  • replacement of outdated tactile paving arrangements to ensure they are compliant
  • the introduction of new high friction surfacing on approach to the crossing

Repainting of existing road markings and replacement of existing high friction surfacing at a crossing are considered maintenance activities so requests for these must use the appropriate reporting tool.

Pedestrian refuge islands can be installed on carriageways where:

  • there is an existing dropped crossing
  • the width is greater than 7.2m, and
  • where a high number of pedestrians are having difficulty crossing the road

Refuge islands provide the opportunity for pedestrians to cross the carriageway in two phases where gaps in the two-way traffic are limited due to the volume of traffic. Pedestrian refuges must be designed to appropriate standards to accommodate the types of user groups expected to be encountered, for example, where cyclists need to be accommodated the refuge island will need to have an increased width.

Costs and timeframes

Indicative costs and timescales for the design and construction of crossing upgrades and refuge islands are given in the table below.

 
Design
Constuction
 
Fee
Duration
Cost
Duration
Zebra Crossing Upgrade £12,250 12 weeks £45,500 10 weeks
Pedestrian Refuge £7,350 10 weeks £19,250 8 weeks

The design duration is measured from the point in time where the scheme has been commenced by the allocated Engineer. The construction durations include the minimum mobilisation time required to provide sufficient time to process the works information and mobilise personnel to undertake the works.

Introduction

Pedestrian guardrail can be considered for installation under LHP to reduce risk to vulnerable users, however there are a number of limitations and alternatives for consideration described below.

Things to consider

Pedestrian guardrail will be used for new sites in order to offer some protection to pedestrians to prevent them straying into the road or crossing at inappropriate locations where it is considered absolutely necessary and where there is a documented history of pedestrian collisions.

Guardrail may also be considered where it is required to offer some protection to pedestrians where the swept path of large vehicles takes them close to the footway or potentially overhanging it. However, this should only be a last resort after the consideration of footway realignment or the use of other features such as trief kerb or overrun areas have been investigated.

For larger schemes at locations with existing pedestrian guardrail, there should be a presumption that the pedestrian guardrail will be removed and only those sections that are identified as providing pedestrian protection will be replaced or kept.

In all instances pedestrian guardrail should be considered for as short a length as possible, and it is a last resort.

Pedestrian guardrail should not be used in residential areas, except at school pedestrian exits, or at junctions or crossing points with a history of pedestrian collisions if it is not possible to implement an alternative design for the junction or crossing. It may be considered at alleyway exits for the width of the exit where it is demonstrated that pedestrians are at risk from stepping out of the alleyway into the carriageway, however, this must consider the needs of all user groups and cannot limit access for disability groups or pushchairs.

In urban areas pedestrian guard railing may be considered where the risk of walking into the carriageway is very high and would result in a higher severity pedestrian casualty, or at junctions or crossing points with a history of pedestrian collisions if it is not possible to implement an alternative design for the junction or crossing.

Pedestrian guardrail shall not be used in rural areas unless there is a demonstrated issue to address such as a rural school.

Vision Zero Considerations: There is much support for removal of pedestrian guardrail as it creates risk for walkers and vehicle occupants/riders if vehicles hit it and this damage increases the burden on the maintenance budget. Pedestrian guardrail should not be required where there is good design and safe speeds.

  • The safe system views pedestrian guardrail as failure of the design process but it is recognised that in certain situations in Essex it may be required as a measure of last resort.

Costs and timeframes

The design cost for pedestrian guardrail is dependent upon the below ground conditions and the impact on statutory undertakers apparatus. This will be unknown until the design process commences.   Construction costs are dependent on the length installed.

 
Design
Constuction
 
Fee
Duration
Cost
uration
Pedestrian guardrail £4,950 6 weeks £3,877.60 6 weeks

The design duration is measured from the point in time where the scheme has been commenced by the allocated Engineer. The construction durations include the minimum mobilisation time required to provide sufficient time to process the works information and mobilise personnel to undertake the works.

Introduction

The Department for Transport (DfT) publishes guidance for Highway Authorities on setting local speed limits.

Essex County Council has a speed management policy that takes into account the effect that appropriate traffic speeds have on environmental and social objectives, as well as their effect on road safety at a national and local level. Both documents place a high importance on consistent and coherent speed management to encourage driver compliance and to seek to reinforce the driver’s assessment of the safe speed to travel.

All schemes put forward should be consistent with national and local policy in order to be promoted for implementation

Things to consider

Speed surveys will be required to establish the actual speeds at the location where a speed limit reduction is being considered. Any LHP scheme request for speed management and/or new speed limits will need to go through the LHP validation process. This is where the request would be investigated and feasible engineering solutions, where possible, to the issues raised would be put forward.

Essex Police are consulted on changes in speed limits. As the enforcing authority of road speed limits their support is an important factor in ensuring any changes are successful in their stated aims.

Any changes to speed limits require a Traffic Regulation Order (TRO). Once this is in place and is correctly signed then the speed limit is legally enforceable. Any enforcement activity would be considered against Police resources at that time. If the legal process is not followed and/or the signing is not correct then the limit cannot be enforced.

Costs and timeframes

Costs and timeframes for speed limit changes cannot be estimated as it would depend on the length of road being considered plus local conditions, statutory undertakers etc. Any changes to speed limits will require a TRO which will add to the cost and timeframe of the scheme.

 
Design
Constuction
 
Fee
Duration
Cost
Duration
Standard Sign Face, Post and Foundation (no TRO) To be determined scheme by scheme

Introduction

Cycling is important to Essex. The demand for cycling in Essex has increased within the last few years, and with this increase we have seen more requests for provisions to assist people who cycle.

Appropriately located and secure cycle parking facilities is a factor which can help to encourage cycle use.

Things to consider

Good practice for cycle parking facilities can be summarised as follows: visible, accessible, safe and secure, consistently available, easy to use, fit for purpose, managed and maintained, attractive, coherent and linked to other needs of cyclists.

Access to safe and secure parking is a major contributor to encouraging cycling. Key locations for cycle parking to be considered include:

  • The Town centre, to access shops and businesses.
  • Railway station, to enable people to cycle to and from the station as part of their journey.
  • Leisure attraction, to encourage cycling and reduce car use.
  • Businesses, to encourage cycling to work.
  • Schools and colleges.

Costs and timeframes

The design and installation cost and duration will depend on the type of facilities being provided.  

 
Design
Constuction
 
Fee
Duration
Cost
Duration
Standard cylce hoop £4,150 6 weeks £5,650.60 6 weeks

The design duration is measured from the point in time where the scheme has been commenced by the allocated Engineer. The construction durations include the minimum mobilisation time required to provide sufficient time to process the works information and mobilise personnel to undertake the works.

Introduction

Raised kerbs at bus stops allow access to the bus services for the mobility impaired, which typically includes the elderly as well as wheelchair and pushchair users.

Things to consider

At bus stops, raised kerbs are normally around 5m in length and require the footway to be reprofiled to accommodate the change in elevation. Where the footway gradients change there may be a requirement to provide additional drainage facilities to ensure surface water is not discharged into adjacent properties or businesses. The position of the bus flag and associated pole may also need relocating to ensure that they are located in an appropriate position to maximise accessibility.

Where the existing facility is located on a verge, consideration must be given to the provision of a hard standing area for passengers waiting to board and alight from the services.

Prior to progressing changes at bus stops, liaison with the Passenger Transport Team will be essential to understand if improvements to existing facilities are planned within the current year to avoid repetition of work, and to establish if the site is still in a serviceable location and doesn’t require relocation or

Costs and timeframes

The design and construction costs for raised kerbs will be dependent on the work required at each individual location.

 
Design
Constuction
 
Fee
Duration
Cost
Duration
Raised kerbs £7,750 6 weeks £11,165 6 weeks

The design duration is measured from the point in time where the scheme has been commenced by the allocated Engineer. The construction durations include the minimum mobilisation time required to provide sufficient time to process the works information and mobilise personnel to undertake the works.

Introduction

Local Authorities can designate country lanes as ‘Quiet Lanes’ in rural areas under the Transport Act 2000.

Country lanes are an integral part of our rural environment but the volume and speed of traffic and the presence of heavy lorries can make them uninviting and intimidating.

Quiet lanes can be a positive way of providing a modal shift to enhance the number of people walking, cycling and riding horses, widening transport choice and protecting the character and tranquillity of the country lane. They should also protect and enhance the local character and distinctiveness of the countryside.

Things to consider

If the road carries more than 1000 vehicles per day, then it cannot be considered for a Quiet Lane. The speed of the vehicles using the road is also important and the 85th percentile must show speeds of less than 35mph.

Only narrow, single-track roads are suitable to be designated as Quiet Lanes. They should be rural in character and ideally be in a rural area to be most effective.

Community involvement is essential to encourage a change in behaviour of road users. When a request is submitted for a Quiet Lane it must have a high level of community support. Formal consultation must be undertaken as part of the process, with both the local and wider community.

It must be noted that designation as a Quiet Lane does not bring about any enforceable restrictions nor does designation prohibit use by any types of vehicle or regulate their speed. The sign reminds road users of the types of traffic they should expected to encounter and encourages them to navigate the route accordingly and at an appropriate speed.

The only physical measure to be implemented would be the national Quiet Lane sign to identify entry into and exit from a Quiet Lane. The Quiet Lanes introduced by ECC have featured a sign and wooden post to ensure that these signs are inconspicuous with the rural setting. ECC will ensure that the landscape features, such as hedges, verges, walls and wayside trees will be sensitively managed to improve the landscape, retain local character and make travel easier for cyclists, walkers and horse riders. Designation as a quiet lane will affect the routine verge cutting.

Costs and timeframes

There is minimal cost associated with the design of Quiet Lanes, however, there is a need for a consultation to be held in a location near the proposed Quiet Lane, which adds time to the scheme programme. The timescale for delivery is subject to the consultation and when this can be held.

 
Design
Constuction
 
Fee
Duration
Cost
Duration
Quiet lane £5,250 18 weeks £1,750 6 weeks

The design duration is measured from the point in time where the scheme has been commenced by the allocated Engineer. The construction durations include the minimum mobilisation time required to provide sufficient time to process the works information and mobilise personnel to undertake the works.

Introduction

Flashing lights (‘wig-wags') are used to indicate the presence of pupils crossing to get to school and operate during appropriate start and finish times.

In Essex, they are available to all schools regardless of whether the location is situated on a county route or local road, provided children are likely to be crossing the road on their way to school.

Things to consider

For installation of Wig-Wags, there must be a single identified crossing site that is used by the school children on their way to and from school.

Wig-wags may also be used where the school warning sign is already in use and where the 85th percentile speed exceeds 35mph, or on a busy road to aid driver attention.

The lights may be used when TSRGD diagram 545 is used together with diagram 546, 547.1 or 547.7 and the crossing point is in use (whether or not it is supervised).

Wig-wag lights should not be used near level crossings, traffic signals, or zebra / controlled crossings as this might cause confusion or distraction. They should never be used to warn of children crossing at zebra or controlled crossings.

The electrical supply for the flashing signs can either come from an existing power source or can be solar powered, dependent upon the site conditions.

Costs and timeframes

Costs and timeframes for the design and installation of signs vary depending on the nature of the sign itself. Where an existing post can be used there is a reduced cost as only the sign plate itself will need to be erected, whereas if it’s a new sign in a location where there isn’t an existing and appropriate post to be used then there will be a need for a new sign post and foundation. Where the speed limit of the adjacent road is in excess of 50mph then there will be a need for a passively safe post and foundation system to be used which will increase costs further. The costs in the table below provide an indicative range, but they are dependent upon the existing environment.

 
Design
Constuction
 
Fee
Duration
Cost
Duration
Mounted on an existing asset £4,250 8 weeks £4,250 10 weeks
Mounted on a new post with foundation £4,950 8 weeks £8,025 10 weeks

The design duration is measured from the point in time where the scheme has been commenced by the allocated Engineer. The construction durations include the minimum mobilisation time required to provide sufficient time to process the works information and mobilise personnel to undertake the works.

Introduction

Managing driver behaviour and encouraging drivers to stay within the speed limit can be achieved in different ways.

Dependent on the location and site conditions, this includes buildouts, various types of surfacing and road humps / speed cushions.

Things to consider

Build outs can be considered where:

  • parking and cycling can be accommodated
  • congestion is not likely, and
  • where any concerns from frontages and bus providers have been addressed.

The build out must include a physical protected cycle bypass lane of at least 1.5m width unless it has been implemented in association with pedestrian crossing facilities. If this is not achievable, an unprotected cycle lane of over 1.5m wide or, where this is not achievable, a maximum running lane width of 3.0m

Rumblewave surfacing is not suitable in residential areas due to noise and vibration. It is largely ineffectual when used alone so it is rarely used as a speed reduction measure. Where it has been installed it has been shown to require regular and expensive maintenance which places a significant burden on the ongoing maintenance budgets.

Red coloured road surfacing is only considered by ECC for use for speed management in association with a collision reduction site or at a gateway to highlight a specific hazard. The limited use is down to several factors including maintenance, its effect on the environment and the cost of installation. There is also a concern that overuse will dilute its effectiveness.

ECC will only implement road humps and cushions as a last resort after all other traffic calming measures have been considered and only on urban local roads. Any proposal for road humps and cushions needs to show why other measures cannot be implemented.

Full consultation with the local community and emergency services must be undertaken for road humps as they must be made aware of any negative impacts that a scheme comprising physical measures might have. This may include noise, discomfort or exclusion for certain user groups, including local disability/access groups, loss of parking in some instances and changes to the visual environment. If road humps are used within a scheme all physical measures relating to this addition will be subject to both informal and formal consultation.

Emergency services and bus operators are generally opposed to road humps so it is important to consult with them at an early stage. In some instances, the bus operators will not use a route with speed humps/cushions and may remove the service. If agreement cannot be reached the community and ultimately the cabinet member for infrastructure will have to consider whether the advantages of the scheme outweigh the possible loss of a bus service.

Vision Zero Considerations: The Place and Movement approach and the Speed Management Strategy (currently under review) are likely to change the face of traffic calming in Essex. We intend to work closely with Essex Police within the Safer Essex Roads Partnership to deliver a plan for speed limits and enforcement across Essex. The scope and scale of speed limit changes will dictate the change in culture amongst Essex residents and road users which, in turn, will determine what physical features may be required to enhance compliance. It is likely that safety cameras and other technology will play the biggest role in future enforcement as physical measures introduce risks to some road users such as bus passengers and motorcyclists.

  • The Safe System guides us to use features which will not introduce risk for any road user and to use features that will be maintained, which includes drainage and lighting, and which will remain visible (especially the signing for the features) even when foliage grows each Spring.

Costs and timeframes

Design and construction costs and duration are dependent upon the type of traffic calming being considered for the location. They will need to include the TRO process in the case of road humps and may be subject to objections that could result in a longer process as the objections are dealt with or a CMA is processed to enable their installation. Indicative costs and durations for the different types of interventions are shown below.

 
Design
Constuction
 
Fee
Duration
Cost
Duration
Build outs £7,350 10 weeks £19,250 8 weeks
Road humps £10,750 18 weeks £26,735 10 weeks

The design duration is measured from the point in time where the scheme has been commenced by the allocated Engineer. The construction durations include the minimum mobilisation time required to provide sufficient time to process the works information and mobilise personnel to undertake the works.

Introduction

Where an existing dropped kerb arrangement for an informal crossing does not have tactile paving, the Panel can consider its introduction.

Things to consider

Tactile paving for an informal crossing will consist of two rows of buff tactile paving and will be accommodated within the confines of the existing dropped kerb arrangement.

An additional potential modification to the existing crossing may be required, dependent upon the height of the existing dropped kerbs. Where the dropped kerbs have a height that is above +6mm, then the dropped kerbs would need to be relayed to ensure they are compliant with standards.

Costs and timeframes

The cost associated with the design and installation of tactile paving is dependent upon the site conditions at the desired location. Where the existing dropped kerbs need relaying the costs will be similar to that of a new dropped crossing (detailed above).

 
Design
Constuction
 
Fee
Duration
Cost
Duration
Tactile Paving £4,350 3 weeks £4,500 6 weeks

The design duration is measured from the point in time where the scheme has been commenced by the allocated Engineer. The construction durations include the minimum mobilisation time required to provide sufficient time to process the works information and mobilise personnel to undertake the works.

Introduction

Handrailing for existing steps can be retrospectively installed by a Local Highway Panel to improve access for those user groups that need additional support when navigating them.

Things to consider

The length of handrailing will be subject to the number of steps and their arrangement, as there will be a need to ensure they are present at all landings. The railing will need to be continuous without any changes in diameter to ensure partially sighted users do not run their hands into obstructions whist travelling.

Costs and timeframes

Design and construction costs and durations will be dependent on the length required and the coating and colour needed at that location, so it is not possible to provide an indicative cost for all potential locations. This will be confirmed once the request has been submitted and the need is established.

 
Design
Constuction
 
Fee
Duration
Cost
Duration
Handrailing to Steps To be determined scheme by scheme