Terminus Street works complete


24/09/2020
Latest News
Latest information relating to the completed works at Terminus Street, Harlow

Read more

Terminus Street, Harlow

[FEATURED_NEWS]

Works Location

 

Photos



The works

Arrangements have been made to resurface Terminus Street and Post Office Road, Harlow. Works are due to start on Tuesday 1 September 2020 and expected to take approximately four weeks to complete.


What is involved and how this may it affect you

Works will take place Monday to Sunday between the hours of 7pm to 5am. In order to support these works it will be necessary to close Terminus Street during working hours. To minimise disruption the works will be completed in phases and the traffic management will be amended during each phases.

Where possible traffic management restrictions will be reduced outside of working hours.

Proposed phases:  
Proposed Phasing   Area affected Proposed traffic restrictions 

Phase 1 and 2

Terminus Street and Post Office Road Overnight road closure on Terminus Street and Post Office Road. Banksmen will be on site to guide buses in order to turn and enter the depot.

Traffic will be diverted via Velizy Avenue, Fourth Avenue, Post Office Road.

The one-way system on Post Office road will temporarily be suspended to allow two-way traffic with the support of traffic lights and a temporary 20MPH speed limit.

Phase 3


Post Office Road  Overnight road closure on Post Office Road.

Traffic will be diverted via Velizy Avenue, Fourth Avenue, Post Office Road.

The one-way system on Post Office road will temporarily be suspended to allow two-way traffic with the support of traffic lights and a temporary 20MPH speed limit.

Phase 4

Post Office Road near East Gate  Overnight road closure on Post Office Road. One –way system will operate as normal.

Banksmen will be on site to guide buses in order to turn and enter the depot.

A Local diversion route will be in place during road closures. We would urge drivers to allow additional travelling time and take care to observe traffic management and signage in place.

A temporary clearway/no parking restriction will be introduced on Post Office Road for the duration of the works. The restriction is necessary to ensure no obstructions are on the road which could cause a delay.

Please refer to the document section for further details on the areas of work.

The car park located on Post Office Road will be operational as usual.

Pedestrian access will be maintained at all times.

Passenger transport

There will be no change to the bus service during the works. During road closures buses will either be guided through the works or a suitable short diversion will be in place. 

Bus bays one and two at the depot will be required for the site compound.

Further information

Dates may be subject to change if affected by poor weather conditions or if unexpected issues arise.

We aim to keep residents and businesses updated via this webpage and site signage. For details about other roadworks in the area, please visit: one.network or the @essexhighways twitter feed.