24 November 2021 Latest News

North Hall Road – Preparations being made for ground investigations

We recently attended site to carry out a topographical survey, this was successful completed, and the results will help us with the progression of the design phase.

We are now in the process of producing a geotechnical specification for ground investigations, during this period you may see minimal activity on site while we prepare the required documentation. These works are anticipated to be carried out in December 2021 with laboratory test results and an interpretive report expected to return in January 2022.

We are also in consultation with the Environment Agency to agree a feasible design solution, once we have agreement on the preferred design, further details can be shared.

A further update will be provided as soon as dates for the ground investigations are confirmed.