Works to re-build the retaining wall along North Hall Road commenced as planned and good progress is being made on site.
The installation of the sheet piles has recently been completed and we are now moving on to the next phase of works which involves the construction of the reinforced concrete capping beam.
We have also carried out temporary make safe repairs to critical areas on the carriageway on Ugley Road.
Our programme continues to be on schedule for completion at the end of October 2022.
The photos below show the sheet piles being installed.