10 October 2024 Priority One

Recently completed Priority One schemes and upcoming road surfacing works

Our recently announced £25million Priority One campaign is helping us get more crews out on the road to tackle the issues that matter. The investment being made will see up to 200 additional resurfacing schemes across the county, as well as works to tidy up vegetation, clear drains and improve signage.

In recent days, we were in Canvey Island, Heybridge and Loughton delivering schemes to tackle road issues that we know frustrate you. A selection of images from these works can be viewed below.

Slideshow of completed works

Hover over image to pause slideshow
 

Cllr Mark Platt, leading the Priority One campaign said, “Through the Priority Once campaign we are undertaking around 200 additional resurfacing schemes as well as vegetation clearance and drainage improvements and we have hit the ground running. Please keep an eye on the Priority One webpage for upcoming works.”

This week, a further three schemes are scheduled. Please note that these works are weather dependant, and therefore dates may change. Works will be carried out overnight to minimise disruption.

Location
Works
Dates
Kings Road, Brentwood Machine Surfacing 15th to 17th October
Gardiners Lane South, Basildon Machine Surfacing 18th to 23rd October
Ashlyns, Pitsea Machine Surfacing 20th October