19 October 2020 Latest News

Safety barrier pre-installation works in progress

Our overnight works to improve the safety barriers to the outer ring of the Broadway Link Roundabout are progressing well.  To date pre-installation works have included resetting kerb inlet gullies, and excavating areas ready to receive concrete.  

Concrete plinth bays are being constructed around the roundabout ready for new vehicle restraint system (VRS) to be mounted on to them, with arrangements made for a specialised contractor to come in later next month to install the VRS.  

Gully cleaning operations are also taking place by our local gully team while traffic management is in place, to maximise efficiency. 

We would like to thank residents and road users for their patience during these works which we aim to complete by 20 November with weather permitting and no unexpected issues arising.