Cookies
We use cookies to give you the best possible experience on our website. You are free to manage this via your browser setting at any time or through the find out more link.
Close
Find out more
Cookie Portal
Manage and find out more about the cookies used on this website.
View Cookie Settings
Read Cookie Policy

Accept All Cookies and Close
Close Without Saving
< Back
This website has 4 types of cookies:
Your preferences will not take affect until the "save and close" button is clicked. To view our cookie policy please click here.
Strictly Necessary Cookies Used to help you move around the site and use its features. Without these cookies, it will be very hard to use the website.
Analytical/Performance Cookies Used to anonymously track visitors around the website so that we can improve your experience.
Functional Cookies Allows the website to remember your preferences and personalised your experience.
Targeted Marketing Cookies Allows adverts you see to be targeted to you and your interests.
Save and Close
< Back
< Back
Cookie Policy
< Back
Search

Abbotsford Bridge, Hall Road, Elsenham

Advance Notice - 14 June 2019: Abbotsford Bridge - revised shuttle bus timetable from 22 June

Following a recent review of the shuttle bus service offered to accommodate passengers affected by the closure of Abbotsford Bridge, a revised timetable will be in operation from 22 June 2019 to reflect passenger usage.

Adjustments will be made to the 7A Monday to Friday shuttle bus timetable, withdrawing the last two journeys of the day; the 1819 / 1835 7A journeys only. The 7A Saturday service will be withdrawn. The main service will continue running as it has been since the start of the bridge closure, with revisions only being made to the 7A part of the route. 

The current timetable will run up to and including Friday 21 June 2019, with the last day of the 7A Saturday service being 15 June 2019.  Please be aware no Sunday or bank holiday service is timetabled.

Please refer to the Trustybus website for timetable details. 

Latest News - 10 June 2019: Abbotsford Bridge - progress update

Since the closure of Abbotsford Bridge on 13 May, a site compound has been established and a temporary footway and lighting installed to provide a pedestrian route during the construction period. This is now in public use.

A temporary bridge is in the process of being installed to support utility supplies that require diverting temporarily.  In the coming days electrical diversions are set to begin.

River diversion works are also in progress.  

To support local people and businesses, additional signage has been placed on the local road network.

We will continue to post updates on this webpage as the scheme progresses.

Highway Schemes Homepage

Works Location

 

Photos

 

About the scheme

Abbotsford Bridge is located to the south east of Elsenham and north of Stansted Airport.  It carries Hall Road, an unclassified road, over Stansted Brook.

The bridge, which consists of a culvert that runs under the road, was originally constructed in two different stages.  The original structure is a cast iron deck supported on cast iron girders constructed in 1880.  This was extended at a later stage on the east side.

Inspections have identified that the structure requires dismantling and replacing as it is now found to be in a weak and deteriorating condition.

Advance vegetation clearance works were carried out in March 2019 in preparation for construction to begin in spring 2019.

 

Main construction

Preparations have been made to commence main construction from 13 May 2019, these works are expected to take approximately six months to complete.

This will involve the installation of a temporary footway prior to the removal of the existing bridge to ensure pedestrian access is maintained. The waterway will be diverted for the works and utility supplies relocated to enable the existing structure to be removed and bridge reconstructed.

During this time a full closure of the road will be necessary, 24 hours a day until the works are complete. 

Advance signage will be on site and following diversion will be in place during the road closure: Hall Road, B1051 (Henham Road, Mill Road, Thaxted Road), Church End, Brick End, Woodgates End, Chapel End, Molehill Green, Waltham Hall Road, Elsenham Road and vice versa.  Care has been taken to choose an appropriate diversion route suited to all vehicles which avoids narrow lanes at Pledgdon Green, i.e. Brick End Road, Henham and Church End Lane. 

 

Clearway/No parking restriction - B1051 High Street/Henham Road junction with Hall Road

Following a request from Elsenham Parish Council, a temporary Clearway/No parking restriction will be introduced on the B1051 High Street/Henham Road at the junction of Hall Road during the closure of Abbotsford Bridge.  This restriction is designed to support traffic flow in the area, providing sufficient space for vehicles who attempt to turn around at the junction of Hall Road.

The temporary Clearway/No Parking restriction will be effective 24 hours a day, 7 days a week for the duration of the bridge closure which commences Monday 13 May 2019. Warning notices will clearly identify the sections of road and periods when parking enforcement is effective.  No parking cones and signage will be in place so please refrain from parking vehicles in these areas when the Clearway/No Parking is in operation.

The Clearway/No Parking areas are enforceable by issuing a Penalty Charge Notice or parking tickets.  In addition, if a vehicle is causing an obstruction and the owner cannot be easily identified then the owner is at risk of the vehicle being moved, by one of our specialised contractors, to a nearby safe parking place.   If this were to happen the owner would be required to contact the Essex County Council contact centre on 0345 603 7631 or Essex Police on 101 who will have details about the whereabouts of the vehicle.

We regret any inconvenience caused however it is essential we enforce a Clearway to ensure the road remains clear without obstructions. 

A plan is included below of the approximate location of the proposed Clearway/No parking restriction for illustration purposes only and can also be referred to on www.roadworks.org.  Areas affected will be clearly identified on site.  

To view details regarding enforcement of the restriction, please also refer to information poster in the Document section below. 

 

Passenger transport

As a result of the bridge closure, TrustyBus route 7/7A which runs between Bishops Stortford and Stansted Airport via Elsenham will be operating a diversion under a revised timetable.  A section of route 7A, covering housing areas on the north side of Stansted Mountfitchet will not be served by the regular bus service, instead a TrustyBus shuttle bus will take passengers from this area to and from the main service 7 at St Mary’s Drive in Stansted. 

  • Service operations up to Friday 21 June 2019:

    Up until Friday 21 June 2019, the temporary shuttle bus will run Monday to Saturday.  Timetable arrangements can be found by viewing information provided by the operator: 

TrustyBus webpage

Temporary TrustyBus Shuttle Bus operation 

TrustyBus Timetable 7/7A/7B/7C/7D/7E

    

  • Service operations from Saturday 22 June 2019:

Following a recent review of the usage of the shuttle bus, adjustments will be made to the 7A Monday to Friday shuttle bus timetable, withdrawing the last two journeys of the day; the 1819 / 1835 7A journeys only. 

The 7A Saturday service will be withdrawn, with the last day being Saturday 15 June 2019. The main service will continue running as it has been since the start of the bridge closure, with revisions only being made to the 7A part of the route. 

Please be aware no Sunday or bank holiday service is timetabled.

 

Further information

The work programme may be subject to change if works are affected by poor weather or if unexpected issues arise.

We will share the latest information about the works and progress updates on this webpage as information as the scheme progresses.

Thank you in advance for your patience and co-operation while we undertake these necessary works.